Chiller Plant - Case study

Chiller plant

The chilled water system consists of three 800-ton electric centrifugal chillers (Chiller 1, 2, 3) and associated pumps. The chilled water system is a variable primary flow design.

challenge

Initial review of past events and trend logs indicated erratic behavior of the Chiller Plant, multiple failures, and difficulty of control, especially during start/stop.

Outcome

Upon completion of this project, all primary issues had been resolved, and the equipment and systems were controlling and operating well, energy consumption and the associated PUE were reduced.

Problems Encountered

The plant had difficulty maintaining temperature control and energy use and PUE values were high

Multiple issues were found to be contributing to both the chilled water system and condenser water systems instability, failures, and increased energy consumption. Extensive control programming and equipment modifications were required to be implemented and functionally tested for verification.

Unique hydraulic conditions, encountered primarily during Chiller staging were causing uncontrolled Chiller failures. Excessive CHWP, CWP, and CT equipment operation was causing unnecessary energy use, equipment wear and reduced operational flexibility. Chiller settings, wiring and control modifications were made to improve response time and temperature control. Extensive control programming and equipment modifications were implemented and tested.

Developing the Strategy

An initial testing plan, intended to model the Chiller Plant under various conditions based on the SOO, was written, and implemented. Subsequent additional investigation and testing was required to achieve the required performance of the Chiller Plant equipment and systems.

The mechanical equipment and control systems were operated over a range of conditions, in various types of unit configurations and multiple types of failure events were tested.

The chilled water pumps are variable speed, controlled by the BMS to maintain adequate flow through the chillers and to the CRAH unit loads. Pressure differential (CHWS<>CHWR) is maintained across the cooling loop for the delivery of chilled water to the cooling units (CRAH’s) in the data center space and electric rooms. The chilled water (CHW) flow requirement for the chillers will be maintained by a minimum pump speed and the control of two bypass valves (Bypass Valves CV-1 and CV-2) in the chilled water mains. The Bypass valves will be controlled so that the minimum flow is always met for each operating chiller evaporator.

results

Chiller settings, wiring and control modifications were made to improve response time and temperature control. Extensive control programming and equipment modifications were implemented and tested.